Washout and Culvert Work 2017

December 2017

Several members installed beaver guards around the two culverts near Parkton on Saturday, December 2. Mark used his S2 motorcar to move equipment from Parkton to the site. Those who helped with the project are Mark Bullard, Phil Gandy and George Newport.

10-07-17-IMG_2740 10-07-17-IMG_1266 (2)   12-02-17-IMG_2775

+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++

October 2017

Recently some of our members met at Clearwater to clean out debris packed in our culvert by beavers.  Our team was led by Mark Bullard, with much help from George Newport and Tim Parnell.  The  culvert is fully open again, and heavy wire screening at culvert ends was fashioned to hopefully prevent future entry of beavers and their associated water-blocking materials.  This work required getting down in the swamp muck, entering places most folks dare not go, and getting done a dirty job.  Much thanks goes to these fellow RS&N recreational railroaders!

10-07-17-IMG_2739     10-07-17-IMG_2738    10-07-17-IMG_1266 (2)

++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++

July 2017

Attached are a series of pictures taken by Doug Bedenbaugh after the contractor has cleared the culverts inlet at Parkton. 

07-04-117-IMG_20170704_111359345      07-04-17-culvert discharge      07-04-17-IMG_20170704_111436541

+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++

April 2017

Eight members turned out for the workday.  The RSN April 1 work crew consisted of Mark Bullard, Doug Bedenbaugh, George Newport, Tim Parnell, Eric Massey, John (Chef) Shefte, Tom Stallings, and Phil Gandy.  Mark had done quite a bit of planning for this project; he purchased the 8x8x10’ treated poles and bought a larger water pump for washing the pilings down. We were able to install two piers to support the rails over the Parkton washout. Chef John had brought and prepared a lunch of delicious hamburgers for the crew – aka Rail BBQ.    Many thanks go out to RSN April 1 Crew Members!!!!!

Washout report pictures by George Newport and Tom Stallings.

We enjoyed the on site cookout so much it was suggested we have a hot-dog cookout late one afternoon and a night ride.

Any one interested?

IMG_2337

Work site before crew began

20170401_171844

Completed Parkton Tressel

20170401_180347

The line is open! Motorcars in Parkton

 

 

 

 

 

 

 

IMG_2339 IMG_2342 IMG_2351 IMG_2353 IMG_2355

 

 

 

 

20170401_113738

 

 

 

 

 

 

20170401_113619 20170401_150609 20170401_170450

 

 

 

 

 

 

 

 

20170401_132829

20170401_13323020170401_133220

 

 

 

++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++

March 29, 2017

RSN again, busy as beavers at the beaver dam, working washout area on March 29.  These guys are as persistent as the beavers working the washout area to get the railway open near the beaver dam. Thanks Mark Bullard, Phil Gandy and Tom Stallings – great job!!

 

20170329_155326

20170329_163341

 

20170329_161026

20170329_155321

 

 

 

 

 

 

 

 

 

 

 

+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++

March 11, 2017

Another washout workday was held on March 11.  A big thank you goes out to Eric Massey, Tim Parnell, Mark Bullard, Phil Gandy and Tom Stallings for spending the day workin’ on the railway….

20170311_103050

20170311_134901

 

20170311_133423

20170311_133425

 

 

 

 

 

 

 

 

 

 

 

 


20170311_143523

 

 

 

 

 

 

 

++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++

March 3, 2017

The group assembled Friday morning at the Green Equipment Facility to gather tools and supplies from the storage areas. Phil loaded his truck and soon after Chris, and Screech did also.  Everyone left the facility site and headed to the work site  The rails removed for the Clearwater washout repair were replaced.  Site work consisted of removing the rails and cross ties that were left in place by the contractor doing the washout repair. Then grading was needed to get the proper elevation for the cross ties to be placed.

Tom stayed behind and replaced the stolen battery in the A4. Safety checks were done on both motorcars and a test drive (ride) was conducted.  Both motorcars are ready for use. Thank you for those that attended the work day: Chris Abbood, Chris (Screech) Lanis, Wally and Rhoda Brown, Phil Gandy, Milton and Ginny Lucas, Jerry Parker, and Tom Stallings.

Chris _Chris_phil

Jerry _Phil toghtening joint bar bolts

 

 

 

 

 

 

 

 

Chris L inserting tie plates

bringing the final rail together

 

 

 

 

 

 

 

 

 

+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++

February 9-11, 2017

Below are pictures of work at Clearwater and Mountaire.  Great work by everyone – Thank you!!!

clearwater wagonclearwater 4

clearwater 5

clearwater wagon 2

 

 

 

 

 

 

 

 

 

++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++

January 27, 2017

Here’s a few pictures of our work session this past Friday, we started at 10am by gathering our tools at the containers in Red Springs, we proceeded up to Clearwater and set up our day. As you can see, after our safety briefing  we had a very productive day and now the site is ready for repair. A BIG thank you goes out to members Phil Gandy, Milton & Ginny Lucas (who brought the machine), and  our track guru, Chris Lainis and his better half Lori. Everyone worked as a well oiled machine and got the job done in about 3 hours. I must apologize that I couldn’t be more help than I was, I am still fighting the lack of lung capacity following my bout with pneumonia over the holidays, thanks to everyone for picking up the slack!   We are planning another work day to repair the damage at Wagon Wheel Road in a few weeks, we have taken measurements and have replacement rail on site,stay tuned for more information!

IMG_2118 (1024x765)

IMG_2106 (1024x765)

 

 

 

 

 

 

IMG_2101 (1024x765)

IMG_2131 (1024x765)